



Project management practice of measuring the difference between planned and actual project progress, calculating whether work is ahead or behind schedule using earned value metrics.
더 불러오는 중......
이 페이지에서
Schedule Variance Analysis
Schedule variance (SV) measures how closely a project's actual progress aligns with its planned timeline. It represents the difference between the value of work completed and the value of work scheduled to be completed by a specific date.
SV = EV - PV
or
SV = BCWP - BCWS
Where:
Related metric from Microsoft Project:
Duration Variance = Duration - Baseline Duration
이와 관련된 다른 항목을 둘러보세요